Installing the UPS: 7372 NCR Voyix SCO Card Only
To install the UPS, follow these steps:
- Lift and remove the Scale Tray off the Bagwell and the set it aside.
- Remove the front and back Bagwell Panels. Do the following:
- Remove four (4) wing nuts from inside the Bagwell to detach the Front and Back Panels, as shown in the image below. Each panel has two (2) wing nuts.
- Pull to unclip the Front and Back Panels from the Bagwell Frame.
- Remove four (4) wing nuts from inside the Bagwell to detach the Front and Back Panels, as shown in the image below. Each panel has two (2) wing nuts.
- Attach the UPS Bagwell Shelf to the Bagwell using two (2) nuts.
- Place the UPS on the UPS Bagwell Shelf.
- Connect the cables to the UPS. For more information, refer to Routing the cables: 7372 NCR Voyix SCO Card Only.
- If immediate or abnormal shutdowns were experienced in the field prior to the UPS battery failure, perform the following steps before replacing the UPS:
- Verify the input voltage status of the UPS.
- Verify that the UPS conversion utility and firmware files are installed on the terminal.
- Convert the UPS voltage to support running environment voltage, if necessary.
- Plug the External AC Cable to the AC wall outlet and turn on the UPS.
- Turn on the POS and then run the ADD utility to ensure the device is updated with the latest firmware.